Advertisment

This Month’s Case Power Consolidation

author-image
PCQ Bureau
New Update

Shilpi Kulkarni was feeling very harried. As the IT Manager of Naveen Trademart, life was never easy. The company had eight offices around the city and it was up to her small team of four people to ensure that everything was up and running all the time. So, when the Chairman announced plans to consolidate all the offices into one building outside the city, she was one of the few to welcome it wholeheartedly. At least, her team would not go crazy traveling from office to office. But now she was beginning to question her own early enthusiasm. 

Advertisment

Though still a good six months away, the logistics of the move were beginning to wear her down. Forget the physical movement, working out the issues of migrating two hundred-plus users, their data and applications from twelve independent servers spread across to the city to the new office was taxing by itself. Added to that was the issue of power management. Faced with frequent interruptions in power, all offices had UPSs. These systems had been bought over the years and were scattered across the various offices. Shilpi had in front of her an inventory of equipment in the various offices.

Head office. PCs: 56; Servers: 4; 10 KVA UPS with external batteries: 1, 2 KVA UPSs: 3; 1 KVA UPS 5; 500 VA 



UPS: 3

Marketing office. PCs: 20; Servers: 2; 5 KVA UPS with external batteries: 1; 1 KVA UPS: 2; 500 VA UPS: 2

Advertisment

Other offices. PCs: 10 approx; Servers: 1; Assorted UPSs of maximum capacity 2 KVA. Some of these UPSs were more than six to seven years old and only constant maintenance kept them going.

Expert Comment  Power Consolidation

Balu Pandian
Marketing Communication Director,

APAC, American Power Conversion
Assumptions:
l PC load is 200 VA each l Redundancy is required on the critical load only
l Server load is 700 VA each l UPSs older than four years need to be scrapped. Hence, all UPSs currently located in the other offices will be disposed off
l Networking load (router/switches/hubs/modem) of 500 VA l All

servers have single corded power supply
l 2 KVA UPSs in other offices l All

UPSs are 1:1, that is,single phase in and single phase out
l Server load plus networking load is critical l Users

are located in separate areas or separate floors that can be powered by

separate UPSs, that is, the load can be distributed
l PC load is non-critical l Since

there are only four people, some level of manageability and pre-failure

diagnostics on the UPS are required
l Minimum backup time needed on critical load is 1 hr on the UPS l Maximum

possible utilization of existing UPS should be implemented to avoid

wastage
l Minimum backup time needed on non-critical load is 30 mins l Backup

time of 2-4 hrs is a must as there are frequent interruptions in power
l Generator backup is of 4 hrs l Assume

expansion in the next one year. Hence, excess capacity of 20% should be

provided for
Solution:
a)

Critical load 
Critical load comes to 10300 VA. This can be calculated by

multiplying the number of servers by load of each server plus load of

networking equipment
14

x 700 + 500 = 10300 VA or 10.3 KVA
Plan

for 15—20% excess capacity for future expansion in the next one year. In

case, further expansion is required, it should be possible to increase the

UPS capacity, without having to buy an additional UPS.
Hence,

the recommended solution for protecting the critical load should be a 12

KVA UPS.
Additionally,

external batteries of the 10 and 5 KVA UPSs need to be attached with this

UPS in order to provide a total of one hour of backup time for the

critical load.
l It

needs to have redundancy, hence capability for additional redundant power

modules
l It

needs to be scalable, hence capability to add additional power modules
l It

is protecting a critical load, hence, in case of problems, should be

easily serviceable. Preferably the design should be modular, so that

faulty components can be easily swapped out. At the same time, it should

be hot-swappable so that the UPS need not be shut down while

servicing/swapping components
b)

Non-critical load
The

non-critical load is 31200 VA. This is calculated by multiplying the

number of PCs to the load of each PC as follows:
156

x 200 = 31200 VA or 31.2 KVA
Plan

for 15-20% excess capacity for future expansion in the next one year. As

and when the requirement increases beyond this capacity, additional UPSs

will be need to be purchased and the oldest existing UPSs phased out.
31.2

x 1.2 = 37.44 KVA is the requirement.
It

is recommend that the assorted UPSs in the other offices be scrapped as

these are older than six years and have outlived their design life. Also

recommend is the scrapping of the 500 VA UPSs.
The

higher KVA UPSs viz,1 KVA/2 KVA/5 KVA/10 KVA can be retained because of

the relatively better reliability and thereby higher design life of higher

KVA UPSs.
Hence

available capacity with existing UPSs = 1x10 + 1x5 + 3x2 +7x1= 28 KVA.
Purchasing

an additional 10 KVA UPS with 20 mins backup time is recommended.
Implementation

of these UPSs for the non-critical load:
l The external batteries on the

10 KVA and 5 KVA UPSs need to be detached and connected with the 12 KVA

UPS powering the critical load.
l All the UPSs powering the

non-critical load, that is, the 1x10 KVA existing UPS, the 1x10 KVA new

UPS, the 1x5 KVA existing UPS, the 3x2 KVA existing UPS and the 7x1 KVA

existing UPS will now have the minimum batteries, that is, for

approximately 15-20 mins.
l These

UPSs need to be distributed across the new building in order to support

the 156 PCs.
l They

will be backed up by the diesel generator (having a capacity of 4 hrs

backup for the entire building load, that is, including AC, lights and IT

load) in case power failure lasts longer than 15 mins. Preferably, this

genset should come equipped with an AMF panel in order to allow for

automatic deployment of the genset shortly after the power failure occurs.
Conclusion
Total

new purchase is 12 kVA UPS with 30 minutes backup time and 10kVA UPS with

15 minutes back up time.
Redeployed

UPSs are 1 KVA (7 nos), 2 KVA (3 nos), 5 KVA (1 no), and 10 KVA (1 no).
Next

Month’s Case 
Other

OS Support
Navneet was faced with a rather unique problem, one he had never faced before and was not sure of how to handle. If it were a technology problem, he would not have had to spend so much time thinking about it. He would have put one of his very able juniors on the job and would have been quite sure that the job would have been taken care of. If push came to a shove, he would have himself sat down to the task. But, like we said, this was not a straightforward technology issue.



Sanjay Kumar had just joined the organization in a fairly senior sales position, from an MNC abroad. Sanjay was eligible for a notebook and Navneet had gone up to ask him about his preferences. In the few days he had been here, Sanjay had created a reputation of being a man on top of his job, but an easy person to work with. Frankly, Navneet had not expected too much in the way of inputs or demands, and, so, was fairly taken aback when Sanjay asked for an Apple PowerBook straight away. His reasoning was very simple. During his many years abroad, he had used a PowerBook extensively, and was not familiar with anything else. His opinion was that he would rather have a notebook that he was comfortable with, and spend his time ensuring that targets are met, than spend the same time learning how to operate a 


new notebook.


Sanjay even found a local Mac dealer who gave a fairly impressive demo. During the demo, Navneet happened to mention that he was looking at adding more storage to his network, and the dealer came back a few days later with a demo for Apple Xserve and RAID storage, connecting them to his network.


Pricing issues apart (Navneet was confident that he could drive a mean deal), he was not sure that he wanted to take on the burden of supporting another OS and architecture. His 400-client/10-server network was based on the Intel architecture and ran Windows and Linux. The Mac was a totally unfamiliar animal to his team. There was also the issue of applications. He had site licenses to most of the regularly used applications (Office Suite, ERP, etc) in the organization. However, he wasn’t sure if Mac software would be easily available or if licenses could be treated as part of the site licenses. Also, a couple of applications were homegrown and there would be issues of porting them or their clients for one man’s use.On the other hand, Sanjay was a very compelling person, and Navneet wasn’t sure if his arguments about not wanting to support a new architecture would be accepted by Sanjay.


Shilpi was fairly sure that she would have to dump a good number, if not all, of the existing UPSs when they moved to the new office. But what should be the exact specs, configuration and topology of the new setup? How much of backup should she provide for? There was going to be a generator in the building. How much redundancy should she provide for, if any? How should she plan for future growth in power needs? Should she buy that capacity today, or should she buy a system that could add capacity as you go along. In fact, were there any with that facility? Also, was it simply a case of just buying any UPS, or was there anything else she could do to optimize power consumption at Naveen Trademart?

Advertisment